Communal activities plan · 2026

Our neighbourhood. Our money.

The current year: what is planned and how has the plan changed? Execution figures will be added once an official report has been processed.

Find your street ↓
Illustration of pavement and park improvements alongside an expense ledger
Municipal works in the neighbourhood. Illustration.

Official total amounts · 2026

Latest reviewed plan amendment: 24 August 2026 · the whole district

Planned
1.818.000,00 €
Reported implementation
Paid
Plan implementation

A plan does not confirm contracted, completed or paid works. A dash means execution data is unavailable in the reviewed plan; it does not mean zero euros.

From overview to individual item

Find a project

Download data (JSON) ↓

Select the report or a version of the plan. Click a location to see amounts, history and sources. Supervision and contingency funds are included in the total.

Number of displayed items: 55

The table includes carried-over commitments, supervision and unallocated funds. The number of items is not the number of separate construction sites.

Charts for the selected items

All charts in this section follow the search, document and filters above.

Shares by local committee

Shares by type of work

Plan, implementation and payments for the selected items

Projects by selected amount

Click a bar for project details. Use the mouse wheel to scroll through the list.

Click a slice or its label to filter. Click the selected label again to remove that filter.

Projects in the neighbourhood

The map follows the same filters and selected amount as the charts. Explore the neighbourhood and click a marker for projects, amounts and Street View.

Markers show approximate street positions, not confirmed work sites or boundaries. Items on the same street share a marker. Street View may show older imagery or be unavailable.

The map loads automatically as you reach it.

Street positions: © OpenStreetMap contributors, ODbL. Financial amounts: official report and selected plan version.

Click a column heading to sort. Click again to reverse the order; the arrow shows the current direction.

Stenjevec communal activities plan · 2026 · amounts in euros
iscrtavanje parkirališnih mjestaMalešnica346,00 €Not provided in the plan
Source ↗
postavljanje ogradeMalešnica3.978,00 €Not provided in the plan
Source ↗
izrada glavnog projektaStenjevec - jug11.250,00 €Not provided in the plan
Source ↗
izrada glavnog projekta "džepne šume"Špansko - jug9.500,00 €Not provided in the plan
Source ↗
izrada projektne dokumentacije za 80 m odvodnjeVrapče - jug2.850,00 €Not provided in the plan
Source ↗
uređivanje kolnikaDonja Kustošija35.500,00 €Not provided in the plan
Source ↗
uređivanje kolnikaVrapče - jug15.000,00 €Not provided in the plan
Source ↗
uređivanje kolnikaVrapče - jug238.000,00 €Not provided in the plan
Source ↗
iscrtavanje parkirališnih mjestaNije naveden18.700,00 €Not provided in the plan
Source ↗
uređivanje kolnikaDonja Kustošija77.000,00 €Not provided in the plan
Source ↗
uređivanje kolnikaDonja Kustošija82.100,00 €Not provided in the plan
Source ↗
nadzorNije naveden5.400,00 €Not provided in the plan
Source ↗
izrada projektne dokumentacije za izgradnju nogostupaŠpansko - jug5.000,00 €Not provided in the plan
Source ↗
izrada krajobraznog elaborata uređenja zelene površineDonja Kustošija3.125,00 €Not provided in the plan
Source ↗
zamjena oglasne pločeDonja Kustošija1.310,00 €Not provided in the plan
Source ↗
zamjena oglasne pločeDonja Kustošija1.310,00 €Not provided in the plan
Source ↗
zamjena oglasne pločeDonja Kustošija1.310,00 €Not provided in the plan
Source ↗
zamjena oglasne pločeMalešnica1.310,00 €Not provided in the plan
Source ↗
uređivanje podloge na školskom igralištuMalešnica48.000,00 €Not provided in the plan
Source ↗
sadnja grmljaMalešnica600,00 €Not provided in the plan
Source ↗
hortikulturno uređivanjeMalešnica14.700,00 €Not provided in the plan
Source ↗
krajobrazno uređenjeMalešnica21.000,00 €Not provided in the plan
Source ↗
krajobrazno uređenjeMalešnica10.300,00 €Not provided in the plan
Source ↗
krajobrazno uređenjeMalešnica8.200,00 €Not provided in the plan
Source ↗
uređivanje igralištaStenjevec - jug187.500,00 €Not provided in the plan
Source ↗
postavljanje visoke zaštitne ogradeStenjevec - jug24.200,00 €Not provided in the plan
Source ↗
postavljanje stolova s klupamaStenjevec - jug5.700,00 €Not provided in the plan
Source ↗
postavljanje klupaStenjevec - jug1.150,00 €Not provided in the plan
Source ↗
postavljanje klupaStenjevec - jug1.700,00 €Not provided in the plan
Source ↗
postavljanje klupaStenjevec - jug1.700,00 €Not provided in the plan
Source ↗
postavljanje stolova s klupamaStenjevec - jug5.400,00 €Not provided in the plan
Source ↗
postavljanje 2 seta stolova s klupamaStenjevec - jug4.300,00 €Not provided in the plan
Source ↗
uređivanje zelene površine i stazaŠpansko - jug107.000,00 €Not provided in the plan
Source ↗
uređivanje dječjeg igralištaŠpansko - sjever281.000,00 €Not provided in the plan
Source ↗
izgradnja šetniceŠpansko - sjever22.800,00 €Not provided in the plan
Source ↗
izrada projektne dokumentacije za uređivanje dječjeg igralištaVrapče - jug3.750,00 €Not provided in the plan
Source ↗
postavljanje znaka zabrane za pseVrapče - jug220,00 €Not provided in the plan
Source ↗
uređivanje dječjeg igralištaVrapče - jug143.500,00 €Not provided in the plan
Source ↗
postavljanje klamerica sa sjeverne strane k.č.br. 3435 i istočne strane k.č.br. 3436 k.o. Donje VrapčeVrapče - jug11.100,00 €Not provided in the plan
Source ↗
uklanjanje ogradeMalešnica2.000,00 €Not provided in the plan
Source ↗
izvedba opločenjaŠpansko - jug15.000,00 €Not provided in the plan
Source ↗
zamjena stalaka za bicikleStenjevec - jug3.900,00 €Not provided in the plan
Source ↗
izmjena podloge u dječjem igralištuStenjevec - jug67.000,00 €Not provided in the plan
Source ↗
izrada troškovnikaNije naveden4.400,00 €Not provided in the plan
Source ↗
nadzorNije naveden5.000,00 €Not provided in the plan
Source ↗
uređivanje zelene površine i postavljanje rampe za bicikleDonja Kustošija34.000,00 €Not provided in the plan
Source ↗
izrada projektne dokumentacije za sanaciju stepenicaMalešnica5.000,00 €Not provided in the plan
Source ↗
sanacija stepenicaStenjevec - jug50.000,00 €Not provided in the plan
Source ↗
uređivanje staze i postavljanje kalota i klupaStenjevec - jug56.000,00 €Not provided in the plan
Source ↗
božićno ukrašavanjeNije naveden5.000,00 €Not provided in the plan
Source ↗
izrada projektne dokumentacije za sanaciju stepenicaStenjevec - jug3.000,00 €Not provided in the plan
Source ↗
izrada projekta javne rasvjeteStenjevec - jug5.700,00 €Not provided in the plan
Source ↗
neplanirani interventni radovi u vezi s nepredviđenim i slučajnim događajima, postupanjem po nalozima komunalnog redarstva, građevinske inspekcije, inspekcije zaštite okoliša te intervencije po primjedbama i prijedlozima građanaNije naveden48.691,00 €Not provided in the plan
Source ↗
izgradnja parkirališta prema PD iz 2025.Špansko - sjever81.500,00 €Not provided in the plan
Source ↗
izrada projektne dokumentacije za izgradnju pump trackaŠpansko - jug15.000,00 €Not provided in the plan
Source ↗
Item details

Street View

Street View may show older imagery.

Open in Google Maps

How did the plan change?

  1. Initial plan ↗Number of items: 501.818.000,00 €
  2. 1st amendment ↗Number of items: 531.818.000,00 €
  3. 2nd amendment ↗Number of items: 511.818.000,00 €
  4. 3rd amendment ↗Number of items: 521.818.000,00 €
  5. 4th amendment ↗Number of items: 541.818.000,00 €
  6. 5th amendment ↗Number of items: 551.818.000,00 €

History links only exactly matching descriptions, locations, committees and groups. A similar name does not confirm that the work is the same.

Sources and data checks

Sources checked on 13 September 2026. Descriptions and amounts come from the City of Zagreb Official Gazette. Every row links to its source document.

Small municipal projects — a separate amount

The initial plan separately lists €491,000.00 for small communal actions by neighbourhood committees. That amount is not included in the overview above.

Send verified data or correction →

Reading the data · all of Stenjevec

The same budget, a changing allocation of priorities

The total plan remains €1,818,000.00 across all six reviewed versions, while the number of items changes from 50 to 55. Behind the stable total is a different allocation: some items are added, others are removed, and money moves between purposes.